Proposal Date
8-3-2016 12:00 AM
Document Type
Funded Project Report
Project Summary
StormWater Park: Plant and Forest Drive
Chuck Taylor, Campus Landscape Architect ($34,000)
The stormwater management park is be located at the corner of Forest & Plant Drive. The storm water park restores the existing wetlands and creates new bio-retention gardens to mitigate the effects of polluted stormwater/soil erosion that impact the campus wetlands.
Unit or Academic Department
Facilities Planning
Amount Granted
$34,400
Amount Spent
$34,400
StormWater Park: Plant and Forest Drive
StormWater Park: Plant and Forest Drive
Chuck Taylor, Campus Landscape Architect ($34,000)
The stormwater management park is be located at the corner of Forest & Plant Drive. The storm water park restores the existing wetlands and creates new bio-retention gardens to mitigate the effects of polluted stormwater/soil erosion that impact the campus wetlands.